Delivery Agreement

The Delivery Agreement (DA) is a statutory requirement of the Plan preparation process under Regulation 9 of the Town and Country Planning (Local Development Plan) (Wales) Regulations 2005 (as revised by the Local Development Plan (Wales) Amendment Regulations 2015), and must be approved by resolution of the Council and the Welsh Government (WG).

Neath Port Talbot Council (NPTC) started work on its Replacement Local Development Plan (RLDP) in 2021. Preliminary findings from the 2022 ‘Call for Sites’, alongside information obtained from our Annual Monitoring Reports, and growth projections indicates that there was a requirement for additional housing land to be identified and existing infrastructure and viability matters that require more time to overcome.

Given this, the Council decided to stop the preparation of the RLDP, and to start again. A Draft Delivery Agreement (DA) was approved by Council on the 4th October 2023, and following consultation was submitted to the Welsh Government. The Report of Consultation can be found below:

The Delivery Agreement was subsequently approved by Welsh Government on the 26th October 2023, and allows NPT Council to formally commence preparation of the Replacement Local Development Plan (RLDP). The DA sets out a 3.5 year process to anticipated adoption of an RLDP in April 2027, with a plan end date of 2038.

The DA’s purpose is to set out:

  • The Council’s RLDP preparation timetable outlining the various stages of plan preparation, when these will be undertaken and when engagement will take place;
  • Details of the Community Involvement Scheme (CIS), detailing who will be involved in the RLDP preparation process and how and when participation and collaboration will occur; and
  • The resources the Authority will invest in plan preparation.

The Timetable for the preparation of the RLDP is set out below:

Definitive

Key stage Timescale
Delivery Agreement November 2023
Pre-deposit Participation / Preparation (Regulation 14) November 2023-September 2024
Call for Candidate Sites November 2023-December 2023
Pre- Deposit (Preferred Strategy) Consultation (Regulation 15) November 2024- December 2024
Deposit Participation / Preparation December 2024- September 2025
Deposit RLDP Consultation (Regulation 17) November 2025- December 2025

Indicative

Key stage Timescale
Submission of RLDP to WG for examination (Regulation 22) June 2026
Independent Examination (Regulation 23) September 2026 – December 2026
Receipt and Publication of the Inspector's Report (Rule 24) February 2027
Adoption of RLDP (Regulation 25) April 2027
Monitoring and Review April 2028

Hard copies of the Delivery Agreement can be found in all the Deposit locations:

  • Neath Civic Centre, Neath, SA11 3QZ
  • Port Talbot Civic Centre, Port Talbot, SA13 1PJ