| Road No | Location | Description | Likely Duration (Days) | Remarks / Contacts |
|---|---|---|---|---|
| A4109 | Crynant to Seven Sisters, O/S the Factory, Crynant | Lay Duct | 03-AUG-26 to 05-AUG-26 3 days | Temporary 2 Way Traffic Control 24 hrs Bus stop suspension |
| A4109 | Intervalley Road, Opp the Jct of Private Road Banwen | Replace a Pole | 05-AUG-26 to 05-AUG-26 1 days | Temporary Multi Phase Traffic Lights 24hrs |
| A4109 | Main Road Aberdulais | Joint Holes | 01-JUN-26 to 12-FEB-27 257 days | Temporary 2 Way Traffic Control 24 hrs Pelican switch off |
| A4109 | Neath Road, Crynant | Inspection of Structure | 19-SEP-26 to 20-SEP-26 2 days | ROAD CLOSED - Diversion in operation |
| A4109 | Park Street 5 Lower Brynamman | New Pole | 03-AUG-26 to 05-AUG-26 3 days | Temporary 2 way traffic 1 day only |
| A4209 | Church Road Seven Sisters | Jointbox and Cabling | 24-AUG-26 to 24-AUG-26 1 days | Temporary 2 way traffic 1 day only |
| A4230 | Main Road , Jct Stanley Place Cadoxton | Defect Repair | 06-AUG-26 to 06-AUG-26 1 days | Temporary 2 way traffic 1 day only |
| A4230 | Main Road, 2 Ynysllynllad Cottages, Jct Maes Gwyn, Cadoxton | New gas Mains | 20-JUL-26 to 31-AUG-26 43 days | Temporary 2 Way Traffic Control 24 hrs |
| A4242 | Harbour Way, Tywi Sewcus Port Talbot | Survey | 03-AUG-26 to 08-AUG-26 6 days | Lane Closure |
| A474 | Commercial Road, 57 Rhydyfro Pontardawe | Vegetation Clearance | 05-AUG-26 to 07-AUG-26 3 days | Temporary 2 Way Traffic Control 24 hrs |
| A474 | Gelligron Road, opp Llety Glynteg, Pontardawe | New Pipe Line | 18-JAN-27 to 05-FEB-27 19 days | Multi Phase Traffic Light 24 hours |
| A474 | James Street, Jct Alltacham Drive, Opp Gwynfa, Pontardawe | Laying new Gas Pipeline | 28-SEP-26 to 16-OCT-26 19 days | Temporary Multi Phase Traffic Lights 24hrs |
| A474 | Neath Abbey Road, Jct A474 Court Herbert Roundabout, Jct Roman Way Neath | New Plastic Gas Mains | 20-JUL-26 to 04-SEP-26 47 days | Temporary 2 Way Traffic Control 24 hrs |
| A474 | Neath Road, 92 Rhos Pontardawe | New Connection | 12-AUG-26 to 14-AUG-26 3 days | Temporary 2 Way Traffic Control 24 hrs |
| A48 | Briton Ferry Bridge, Baldwins Crescent Neath | Civil Works | 01-AUG-26 to 02-AUG-26 2 days | South Bound Fast Lane Closure |
| A48 | Earlswood to Briton Ferry Bridge to Baldwin Crescent | Grass Cutting | 01-AUG-26 to 02-AUG-26 2 days | Fast lane Closures East and West Bound |
| A483 | Fabian Way, Amazon Roundabout, Jersey Marine | Signal Changes | 03-AUG-26 to 07-AUG-26 5 days | Slow Lane Closure East and West Bound |
| B4242 | Ponterneathvaughan Road, Glynneath | Layby Works | 02-JUL-26 to 14-AUG-26 44 days | Temporary 2 Way Traffic Control 24 hrs |
| B4283 | Water Street, Ty DDU, Margam | Drainage Works | 20-APR-26 to 31-AUG-26 134 days | Temporary 2 Way Traffic Control 24 hrs |
| B4286 | Cwmavon road, Jnc Pantdu Cwmavon | Blockages | 20-JUL-26 to 21-JUL-26 2 days | Temporary 2 Way Traffic Control 24 hrs |
| B4287 | Afan Valley Road, Jct Pine Grove, Cimla | Active Travel Scheme | 16-MAR-26 to 31-AUG-26 169 days | Multi Phase Traffic Light 24 hours Time On/Off Site: 09:30 24 hours manned 7-7 |
| B4287 | Efail Fach, 10, Pontrhydfen | Renew a Service | 31-JUL-26 to 04-AUG-26 5 days | Temporary 2 Way Traffic Control 24 hrs |
| B4434 | Commercial Road, Resolven | create safe area to work/storage | 11-MAY-26 to 14-AUG-26 96 days | Temporary 2 Way Traffic Control 24 hrs |
| B4434 | Dulais Fach Road Adj 4-10 Tonna | New Gas pipe Lines | 10-AUG-26 to 11-SEP-26 33 days | Temporary 2 Way Traffic Control 24 hrs |
| B4434 | Lletty Dafydd Clyne | Maintenance works | 14-SEP-26 to 26-SEP-26 13 days | ROAD CLOSED - Diversion in operation |
| B4603 | High Steeet Ynysmeudwy Pontardawe | Tree Cutting | 21-JUL-26 to 21-JUL-26 1 days | Temporary 2 way traffic 1 day only |
| B4603 | Swansea Road Tebanos | Civil Works to Retaining Wall | 13-FEB-26 to 31-DEC-26 322 days | Temporary 2 Way Traffic Control 24 hrs |
| U/C | Aberdare Road , Between Ynyslas Crescent, Jct Pontneathvaughan Road, Glynneath | New Sewer | 20-OCT-26 to 26-FEB-27 130 days | Temporary Multi Phase Traffic Lights 24hrs Bus Stop Suspension |
| U/C | Access Road to Tesco, Gwyn's Drift, Pontardawe | New Site | 27-JUL-26 to 21-AUG-26 26 days | Multi Phase Traffic Light 24 hours |
| U/C | Alloy Industrial Estate, o/s Wall Colmonoy Pontardawe | Joint hole in Footway new supply | 18-AUG-26 to 24-AUG-26 7 days | Temporary 2 Way Traffic Control 24 hrs |
| U/C | Beacons View Cimla | Sewer | 29-JUN-26 to 30-AUG-26 63 days | ROAD CLOSED - Diversion in operation |
| U/C | CEFN COED ROAD, CWMAVON | New Pipe Lines | 20-JUL-26 to 07-AUG-26 19 days | ROAD CLOSED - Diversion in operation |
| U/C | Coedcae, 3, Pontardawe | New Connection | 05-AUG-26 to 10-AUG-26 6 days | ROAD CLOSED - Diversion in operation New Service |
| U/C | Commercial Street, Seven Sisters | Joint Box | 24-AUG-26 to 24-AUG-26 1 days | ROAD CLOSED - Diversion in operation |
| U/C | Dan Y Bryn Road Port Talbot | New Cables | 22-JUN-26 to 05-AUG-26 45 days | Temporary Multi Phase Traffic Lights 24hrs |
| U/C | Drummau Road, Skewen | Cabling Works | 21-SEP-26 to 21-SEP-26 1 days | ROAD CLOSED - Diversion in operation |
| U/C | Dwr Y Felin Road Neath | Gas Mains Replacement | 20-JUL-26 to 04-SEP-26 47 days | ROAD CLOSED - Diversion in operation |
| U/C | Glan Gwrelych, O/S Aber, Pontwalby, Glynneath | Clear Blockages | 24-AUG-26 to 26-AUG-26 3 days | ROAD CLOSED - Diversion in operation |
| U/C | Hill Road, 14 Neath Abbey | Leaking Pipe | 31-JUL-26 to 04-AUG-26 5 days | ROAD CLOSED - Diversion in operation |
| U/C | King Street, from Under the Motorway to Jct Forge Road Port Talbot | Cable Works | 08-JUN-26 to 14-AUG-26 68 days | ROAD CLOSED - Diversion in operation |
| U/C | Lane Rear of 23-30 Ynys Street Port Talbot | New cables | 26-JUN-26 to 17-AUG-26 53 days | Temporary 2 Way Traffic Control 24 hrs |
| U/C | London Row, Jct Ty'r Owen Row o/s 20 Cwmavon | New Service Pipes | 30-JUL-26 to 19-AUG-26 21 days | Temporary 2 Way Traffic Control 24 hrs |
| U/C | Mirfa Road, Saltoun Street, Heol Y Gwrgan, Brynhyfryd Road, Margam | Surveys Route Prior to Potential New Water Main | 13-AUG-26 to 19-AUG-26 7 days | Temporary Multi Phase Traffic Lights 24hrs |
| U/C | Monastery Road, Neath Abbey | Bridge Survey | 04-SEP-26 to 05-SEP-26 2 days | ROAD CLOSED - Diversion in operation |
| U/C | Old Wern Road, 72 Ystalyfera | Repair Leaking Ferrule | 01-SEP-26 to 03-SEP-26 3 days | ROAD CLOSED - Diversion in operation |
| U/C | Pant Howell Ddu, from Laytlin View Neath | Replace a Pole | 02-SEP-26 to 02-SEP-26 1 days | ROAD CLOSED - Diversion in operation |
| U/C | Pant Yr Arian, 5 Baglan | Repair Leaking Ferrule | 19-AUG-26 to 21-AUG-26 3 days | ROAD CLOSED - Diversion in operation |
| U/C | Primrose Lane , 9 Rhos Pontardawe | Sewer | 04-AUG-26 to 08-AUG-26 5 days | Temporary 2 Way Traffic Control 24 hrs |
| U/C | Railway Terrace, 8, Cwmllynfell | New Pole | 28-AUG-26 to 28-AUG-26 1 days | ROAD CLOSED - Diversion in operation |
| U/C | Rhiw Road, Between Heol Y Goedlan and Rhiwfawr Road, Rhiwfawr | Installing Fibre Telecom | 25-JUN-26 to 10-AUG-26 47 days | Temporary Multi Phase Traffic Lights 24hrs |
| U/C | Saltoun Street, 26-Jct Knox Street Maximin Road, Knights Road Margam | leaking pipe | 13-AUG-26 to 20-AUG-26 8 days | Stop/Go Boards |
| U/C | Saltoun Street, o/s 26 to Jct Knox Street, Maximin Road, Knights Road Margam | Survey for Potenyial new water Main | 13-AUG-26 to 20-AUG-26 8 days | Stop And Go Convoy |
| U/C | Tydraw Place , 48 Station Road Port Talbot | Ducting | 27-APR-26 to 05-AUG-26 101 days | Multi Phase Traffic Light 24 hours |
| U/C | Tydraw Street, 48, Port Talbot | New Cable Duct | 20-JUL-26 to 03-AUG-26 15 days | ROAD CLOSED - Diversion in operation |
| U/C | Water street, Opp Jct Pembroke Terrace, 148 Aberavon | Duct in Footway | 06-AUG-26 to 10-AUG-26 5 days | Temporary Multi Phase Traffic Lights 24hrs Traffic sensative |
| U/C | Waun Sterw, Cysood Y Bro, Rhydyfro Pontardawe | Defective Box | 19-AUG-26 to 21-AUG-26 3 days | Temporary Multi Phase Traffic Lights 24hrs |
| Church Crescent Blaengwrach | TM Purooses | 20-JUL-26 to 22-JUL-26 3 days | Temporary 2 Way Traffic Control 24 hrs | |
| Dyffryn Road, O/S Woodcutters Cottage Bryncoch | New Pole | 18-AUG-26 to 18-AUG-26 1 days | ROAD CLOSED - Diversion in operation | |
| Pen Y Dre, 56, Neath | New Cabinet | 15-SEP-26 to 15-SEP-26 1 days | ROAD CLOSED - Diversion in operation |