Gwaith ar y Ffordd a Cau Ffyrdd

Ewch i Traffig Cymru i gael gwybodaeth am waith traffyrdd a chefnffyrdd. 

Local Road Works
Road No Location Description Likely Duration (Days) Remarks / Contacts
A4068 Bryn Road, Coedffaldau Road Lower Brynamman New Pole 27-APR-26 to 30-APR-26 4 days ROAD CLOSED - Diversion in operation
A4107 Afan Valley Road, approximately 250 meters east of its junction with the B4287, Pontrhydyfen Landslide (Core Highway TTL's 31-OCT-25 to 30-APR-26 182 days Temporary 2 Way Traffic Control 24 hrs
A4109 Main Road, Jct Dulais Drive, Adj 4 Ffynnon Dawel Aberdulais New Mains 16-FEB-26 to 17-APR-26 61 days Temporary 2 Way Traffic Control 24 hrs Pelican Switch off
A4109 Church Road 81 Seven Sisters New Gas Supply 20-APR-26 to 01-MAY-26 12 days Temporary 2 Way Traffic Control 24 hrs
A4230 Church Road, Main Road, Cadoxton Gas Mains Replacement 16-FEB-26 to 28-APR-26 72 days Multi Phase Traffic Light 24 hours Date amended to 16.02.2026
A4241 Afan Way, Jct of Water Street Aberavon Neath drainage works 23-APR-26 to 13-APR-26 -9 days ROAD CLOSED - Diversion in operation The alternative route for vehicular traffic north bound on Afan Way will be via Harbour Way, Harbourside Road & Water Street.
A4241 Harbour Way from Roundabout Juction A48 in a northerly direction for a distance 2.5km along its length, Margam Traffic Management for Safety reasons and speed reduction on place 26-JAN-26 to 30-APR-26 95 days East Bound Slow Lane Closure
A474 Briton Ferry Road, 45 Neath New Cabinet 22-APR-26 to 22-APR-26 1 days Stop Go Boards 1 day only This is a one-day notice and proposed to work off peak between 09:30 – 15:00 - Pelican is not required to be turned off
A474 James Street,Jct Allt-Y- Cham Drive Pontardawe Site extraction of carriageway 13-APR-26 to 15-APR-26 3 days Multi Phase Traffic Light 24 hours
A48 Margam Roundabout to Pyle Road, Adj Cross Hill, 2 Margam Trenching 13-APR-26 to 15-APR-26 3 days Temporary 2 Way Traffic Control 24 hrs
A483 Fabian Way, Jersey Marine. Neath Port Talbot Contra Flow and Resurfacing works east & west bound Lane Closures and Total Periodic Closures for resurfacing works 03-JUL-25 to 30-APR-26 302 days Lane Closures
B4242 HIGH STREET OUTSIDE CO-OP STORE GLYNNEATH WORKS TO ROOF OF CO-OP STORE 12-APR-26 to 12-APR-26 1 days Temporary 2 way traffic 1 day only
B4282 Maesteg Road Bryn Emergency repairs to retaining wall 05-MAR-26 to 17-APR-26 44 days Temporary 2 Way Traffic Control 24 hrs
B4287 Afan Valley Road Jct Cae Rhys Ddu Cimla Civil Engineering works 0930hrs to 1500hrs 30-MAR-26 to 17-APR-26 19 days Multi Phase Traffic Light 24 hours
B4287 Afan Valley Road, Jct Bwlch Road, Cimla Crescent, Cimla Resurfacing works 15-APR-26 to 16-APR-26 2 days ROAD CLOSED - Diversion in operation
B4287 Afan Valley Road, Jct Pine Grove, Cimla Active Travel Scheme 16-MAR-26 to 31-MAY-26 77 days Multi Phase Traffic Light 24 hours Time On/Off Site: 09:30 24 hours manned 7-7
B4287 Cimla Road, Bwlch Road Jct, Cimla Engineering Works 15-APR-26 to 22-APR-26 8 days ROAD CLOSED - Diversion in operation
B4287 Main Road, O/S 20, Pontrhydyfen New Pole 13-APR-26 to 15-APR-26 3 days Temporary 2 Way Traffic Control 24 hrs
B4434 Harley Street, Gnoll Road, Neath Site extraction of carriageway 13-APR-26 to 15-APR-26 3 days Multi Phase Traffic Light 24 hours
B4434 Heol Caredig, Tonna Uchaf, Tonnau New Cabinet 14-APR-26 to 14-APR-26 1 days Multi Phase Lights 1 day only
B4434 Neath Road, 20 Tonnau New Cabinet 13-APR-26 to 14-APR-26 2 days Temporary 2 Way Traffic Control 24 hrs
B4599 Yr hen Residential Home, Gurnos Road, Ystylyfera Demolition works 16-FEB-26 to 30-APR-26 74 days Temporary 2 Way Traffic Control 24 hrs
B4603 Heol Las & Gwrhyd Road Pontardawe Cabling 07-APR-26 to 14-APR-26 8 days ROAD CLOSED - Diversion in operation
B4603 Swansea Road Tebanos Civil Works to Retaining Wall 13-FEB-26 to 31-MAY-26 108 days Temporary 2 Way Traffic Control 24 hrs
C175 Rhiw Road, junction of Mynydd Bach Rhiwfawr New Pole 12-APR-26 to 12-APR-26 1 days ROAD CLOSED - Diversion in operation
C250 Cymmer to Glyncorrwg, Cymmer Rd Cymmer Joint Box 15-APR-26 to 16-APR-26 2 days Temporary 2 Way Traffic Control 24 hrs
U/C Alltygrug Farm Road, Ystalyfera Mnhole Cover 12-APR-26 to 12-APR-26 1 days Stop And Go Convoy
U/C Beechwood avenue, Jct Cimla Road , Westernmoor Road, Neath Site extraction of carriageway 13-APR-26 to 15-APR-26 3 days Multi Phase Traffic Light 24 hours
U/C Church street, Wharf Road, Briton Ferry New Pole 09-APR-26 to 13-APR-26 5 days Multi Phase Traffic Light 24 hours
U/C Dunraven Street, 1 opps 20 Cwmgwrach Duct 13-APR-26 to 15-APR-26 3 days
U/C Fforch Dwm Road Church House Railway Terrace Tonmawr carrying out Ground check 20-APR-26 to 08-MAY-26 19 days ROAD CLOSED - Diversion in operation
U/C Forge Road Underbridge of Motorway to Jct King Street Port Talbot Cabling Works 26-JUN-26 to 17-AUG-26 53 days Temporary Multi Phase Traffic Lights 24hrs
U/C Graig Road Alltwen Pontardawe Gas Service 21-APR-26 to 24-APR-26 4 days Temporary 2 Way Traffic Control 24 hrs
U/C Heol Cae'r Bont Margam Clearing Vegetation 15-APR-26 to 29-APR-26 15 days ROAD CLOSED - Diversion in operation
U/C Heol Y Felin side of 23 High Street Cwmgwrach T M Purposes 15-APR-26 to 17-APR-26 3 days Multi Phase Traffic Light 24 hours
U/C High Street Jct B4242 to Cwmgwrach Cwmgwrach clear blockages 09-APR-26 to 17-APR-26 9 days Temporary Multi Phase Traffic Lights 24hrs
U/C Junction of Courtland Place and Station Rd, Port Talbot Ducting Works 11-MAY-26 to 19-JUN-26 40 days Multi Phase Traffic Light 24 hours
U/C Milboro, Tanywern Lane, Ystalerferaugh Road Manhole 12-APR-26 to 12-APR-26 1 days Stop And Go Convoy
U/C Ochr Y Waun, Adj to Jct of Harris Road Cwmllynfell Blockages 06-MAY-26 to 08-MAY-26 3 days ROAD CLOSED - Diversion in operation
U/C Old Wern Road Ystalyfera Maintenance Work 11-MAY-26 to 13-MAY-26 3 days ROAD CLOSED - Diversion in operation
U/C Pant Howell Ddu, Neath Replace a Pole 28-MAY-26 to 29-MAY-26 2 days ROAD CLOSED - Diversion in operation
U/C Penscynor Outside Windsor House Cilfrew Civil Engineering works 15-APR-26 to 17-APR-26 3 days Temporary 2 Way Traffic Control 24 hrs
U/C Rhiw Roa, Jct Mynydd Bach, Rhiwfawr civil engineering and maintenance works 12-APR-26 to 12-APR-26 1 days ROAD CLOSED - Diversion in operation
U/C Victoria Road, Sandfields Site extraction of carriageway 20-APR-26 to 22-APR-26 3 days Multi Phase Traffic Light 24 hours
U/C ffordd Amazon o/s Kings Dock Building, Crymly Burrows New Pole 16-APR-26 to 20-APR-26 5 days Temporary 2 way traffic 1 day only
U/c Penscynor, O/S Windsor House, 1 Cilfrew Lay Duct 15-APR-26 to 17-APR-26 3 days Temporary 2 Way Traffic Control 24 hrs